So…..things are on hold for one month. We can’t frame unless we know the trusses are on their way, we’ve ordered them, but they’re taking almost twice as long as usual so we’ll need to wait to start framing.
We’ve had the measurements taken for the trusses and the plans are currently being engineered. That should take about a week. Trusses MAY be ready around Thanksgiving, we can start framing about a month before the trusses arrive. So this means we have three to six weeks where nothing is happening on the lot.
In the meantime maybe I can build our own trusses…..

Nevermind.
So…..crickets.